Boca Raton Project Tracker

North Park's New Skatepark & Recreation Complex: What's Coming to This Corner of Boca Raton

Approved and under contract. Not yet built.

By Christine DekantUpdated

Representative image of a skatepark elsewhere — not the North Park design, which has not been built. Photo by Reinis Brūzītis / Unsplash.

Project status

Last verified

Current status
Design approved and a construction contract awarded by the District; the City cleared the site plan on September 3, 2026. Construction of the skatepark has not started, and no permit issuance, build date or opening date is on the record.
Lead agency
The Greater Boca Raton Beach & Park District, which owns the land, approved the design and holds the construction contract. The City of Boca Raton is the land-use and permitting authority, not the project owner.
Location
North Park — the former Ocean Breeze golf course property in Boca Teeca, which the City identifies as roughly 69.49 acres of a 74.72-acre site at 5800 NW 2nd Avenue. The skatepark sits on the southern portion.
Approved design
A multi-use street course, pump tracks, and transition and bowl areas, with shaded green space, landscape buffering and low-impact lighting.
Contract
Roughly $3 million to American Ramp Company through a Sourcewell cooperative purchasing contract, approved May 4, 2026 — with construction to proceed only after permitting and City approvals.

Not confirmed by any primary source

  • The City’s share of the cost. The District says the City committed to two-thirds of construction, but no council vote, resolution or executed interlocal agreement for the skatepark is on the record.
  • A total project cost. The $3.6 million figure in circulation appears only in press coverage; the District’s own approved contract is about $3 million.
  • The facility’s size. Figures from 42,000 to 60,000 square feet have been reported, with no single official number published.
  • Building permits, a construction start, and an opening date.
  • Final parking arrangements for the skatepark, and whether it gets its own address.

The District's North Park project page(opens in a new tab)

The amenities, sorted by how settled they are

Approved in the skatepark design

  • A multi-use street course, pump tracks, and transition and bowl areas — the concept the District board approved on January 20, 2026
  • Shaded green space, landscape buffering and low-impact lighting, approved as part of that concept
  • A site plan for the southern portion of North Park, cleared by the City on September 3, 2026
  • A construction agreement with American Ramp Company for roughly $3 million, awarded May 4, 2026

Elsewhere at North Park, on its own track

  • The traffic garden opened in August 2025 — built and in use
  • Boca Paddle, the pickleball and padel complex, is under construction
  • Trails, a dog park and a playground on the east side broke ground on September 3, 2026 — a separate phase from the skatepark
  • A field house and aquatic facilities remain conceptual, with no approved design

What actually happened, in order

The short version: this is no longer a sketch, and it is not a construction site either.

The Greater Boca Raton Beach & Park District board approved the design in January 2026 and told its consultants to prepare construction documents and pursue permits. In May 2026 the board awarded a construction contract of about $3 million — explicitly conditioned on permitting and City approvals landing first. In July 2026 the District's executive director gave City Council a briefing, which is the presentation an earlier version of this article was built around. On September 3, 2026 the City's Planning & Zoning Board took final action on the site plan amendment that authorizes the skate park on the southern portion of North Park.

What has not happened: a skatepark groundbreaking. The District did break ground at North Park on September 3, but on the east side of the property — trails, a dog park and a playground. That is a separate phase, and conflating the two is the single easiest mistake to make with this project.

Who runs Boca's parks, and why it matters here

A fact that surprises people relocating to Boca: the Greater Boca Raton Beach & Park District is a separate, independently elected special taxing district — not a department of the City. It has its own board, its own budget and its own millage on your property tax bill, and it owns North Park, which it bought as a defunct golf course in 2018.

That split explains why this project keeps appearing in two places. The District owns the land, approves the design and signs the contracts. The City is the land-use and permitting authority, which is why the September step happened at a City board rather than a District one, and why the July Council item was a briefing rather than a vote.

Practically: if you want to know whether the project moved, watch the District. City agendas tell you about permits and land use.

What we still don't know

  • Who is paying for what. The District says the City committed to two-thirds of construction cost. We could not find a council vote, a resolution, a budget line or an executed interlocal agreement for it, so treat the split as asserted rather than settled.
  • The total cost. The District's own approved contract is about $3 million. The $3.6 million total quoted in press coverage does not appear in any primary document we could find.
  • How big it is. Reported sizes run from 42,000 to 60,000 square feet. The District does not publish a figure on its project page.
  • When. No permit issuance, construction start or opening date is on the record.

If you live nearby, or are buying nearby

This is a real facility heading toward construction near homes, so the neutral version is worth stating plainly.

An active recreation facility brings use: cars, arrivals and departures, and noise that carries differently outdoors than indoors. The approved design includes landscape buffering and low-impact lighting, and the District has described the skating features as sitting more than 300 feet from homes. Construction itself is its own period of trucks, dust and noise, whenever it begins.

Whether that reads as an amenity or an intrusion depends on where a specific home sits relative to the site and on when the facility is actually in use. Walk the property at the hours you would care about before you draw conclusions, and read the approved site plan rather than a listing description. We don't predict what any of this does to prices, and you should be skeptical of anyone who does — particularly a marketing sheet that lists an unbuilt park as a feature.

Our take

Further along than most people realize, and further from opening than the September groundbreaking coverage suggested. A design is approved, a contractor is under contract, and the City has cleared the site plan — which is a genuinely different stage from where this article started in July.

The honest position is still: watch it at the source, and don't assume a build date exists until the District publishes one.

Project timeline

Only milestones that appear in District minutes, City agendas or official District announcements. Where a detail is reported but not in a primary record, it is left out.

  1. The District buys the Ocean Breeze golf course

    The defunct course in Boca Teeca becomes the property now called North Park.

    District: North Park project(opens in a new tab)

  2. First skatepark design workshop

    Public input session funded through a Plant-A-Park grant.

    District: workshop provides skatepark input(opens in a new tab)

  3. Second design workshop

    Held with the District, its designers and American Ramp Company.

    City: recreation projects page(opens in a new tab)

  4. District board approves the design

    The board unanimously approved the conceptual design for the skatepark and pump track and authorized construction documents and permitting.

    District minutes, January 20, 2026 (PDF)(opens in a new tab)

  5. Construction contract awarded

    The board unanimously approved an agreement with American Ramp Company for about $3 million, with construction to proceed only once permitting and City approvals are complete.

    District minutes, May 4, 2026 (PDF)(opens in a new tab)

  6. Presentation to City Council

    The District's executive director briefed a Council workshop. A presentation, not a vote — this is the item the earlier version of this article was written from.

    City Council workshop agenda(opens in a new tab)

  7. City clears the skatepark site plan

    The Planning & Zoning Board took final action on an amendment authorizing construction of the skate park on the southern portion of North Park.

    Planning & Zoning agenda, September 3, 2026(opens in a new tab)

  8. Groundbreaking — but for the east side, not the skatepark

    The District broke ground on North Park's trails, dog park and playground. The announcement does not mention the skatepark, which remains unbuilt. It is an easy one to misread.

    District: breaking ground at North Park(opens in a new tab)

As of the last verified date above, no skatepark-specific item appears on the District or City meeting calendars. We add a milestone here only when an official record shows one.

How to follow updates

The District leads the project because it owns the land, approved the design and holds the contract, so its board is where status actually changes; City agendas show the permitting and land-use steps rather than final project decisions.

This page is updated only when an official milestone changes, and the "last verified" date above says when we last checked.

Community Guide

Neighborhoods, schools, prices, and lifestyle — all in one place.

Living in Boca Raton →
Cover of the Palm Beach County Market Report, September 2026, prepared by Christine Dekant and John Oliver of DO Homes Group

Free — September 2026 Palm Beach County Numbers

What Palm Beach County Homes Actually Sold For

In September 2026, the typical house sold for $656,000 and went under contract in 43 days, at 94.7% of asking. Condos are a different market: 6.8 months of supply and 53 days. See both, and what each means for your offer or your asking price.

Boca Raton Market Trends

Live data from the local MLS.

Homes for Sale in Boca Raton

Single-family homes $500k+, updated daily.

Frequently Asked Questions

What is being built at North Park in Boca Raton?

A skatepark and pump track. The Greater Boca Raton Beach & Park District board approved the design in January 2026 — a multi-use street course, pump tracks, and transition and bowl areas, with shaded green space, landscape buffering and low-impact lighting — and the City cleared the site plan on September 3, 2026. Separately, North Park already has a traffic garden that opened in 2025, a pickleball and padel complex under construction, and trails, a dog park and a playground that broke ground in September 2026.

Has the North Park skatepark been approved and funded?

The design is approved and a construction contract of roughly $3 million was awarded to American Ramp Company in May 2026, conditioned on permitting and City approvals. The funding split is less clear: the District says the City committed to two-thirds of construction cost, but no council vote, resolution or executed interlocal agreement for that is on the public record, so treat it as asserted rather than confirmed.

Has construction started on the North Park skatepark?

No. The District broke ground at North Park on September 3, 2026, but that was for the east-side trails, dog park and playground — a separate phase. No permit issuance, construction start or opening date for the skatepark is on the record.

Who manages Boca Raton's parks?

The Greater Boca Raton Beach & Park District, an independently elected special taxing district with its own board, budget and millage rate — separate from City Council and Palm Beach County. It owns North Park, which it bought as a defunct golf course in 2018. The City of Boca Raton is the land-use and permitting authority for projects on District land, which is why approvals for this project happen at both.

Where is North Park located in Boca Raton?

It is the former Ocean Breeze golf course property in the Boca Teeca area. City records identify the site as roughly 69.49 acres of a 74.72-acre property at 5800 NW 2nd Avenue, with the skatepark on the southern portion. A separate address for the skatepark itself has not been published.

How do I check the current status of the project?

Use the District's North Park project page and its board agendas and minutes, since the District owns the land and approves the design and contracts. City agendas cover the permitting and land-use steps. Both are linked in the 'How to follow updates' section of this article.

This article is provided by DO Homes Group at Premier Brokers International for informational purposes only and does not constitute legal, financial, tax, or investment advice. Market statistics, pricing, availability, HOA fees, and community details change frequently and may have changed since publication. School assignments, boundaries, and ratings may change — verify all school information directly with the appropriate school district, and consult official public safety resources for any crime data relevant to your search. Verify all details independently and consult the appropriate licensed professionals before making any real estate decision. DO Homes Group is committed to Equal Housing Opportunity and does not discriminate on the basis of race, color, religion, sex, handicap, familial status, or national origin.